The HiSmelt Lateral Pipeline is a distribution pipeline built in 2004 and owned by APA Parmelia.
The pipeline has a diameter of DN200, capacity of 4.6TJ/day and a length of 1.4km. The Hi Smelt Lateral Pipeline interconnects with the Parmelia Gas Pipeline mainline and is a single shipper pipeline.
This pipeline was built in 2003.
The HiSmelt Lateral Pipeline is currently a non-scheme pipeline and is subject to the access regime for non-scheme pipelines under Chapter 6A of the NGL and Part 23 of the NGR. On 8 May 2023, the ERAWA granted a five-year Category 2 and 3 exemption under Part 23 to the HiSmelt Lateral Pipeline.