AWE Perth Pty Ltd

WA: Waitsia Export Pipeline

The Waitsia Export Pipeline (WEP) is a transmission pipeline located south-east of Dongara, Western Australia. It comprises two sections, the main section of the WEP under Pipeline Licence 124 and the Waitsia to PL 124 Export Pipeline under Pipeline Licence 128. The WEP is also owned and operated by AWE Perth Pty Ltd and Beach Energy (Perth Basin) Pty Ltd.

The WEP under Pipeline Licence 124 is 3.67 km in length, 355.6 mm in diameter, and has a maximum capacity of 350 TJ/day.

The WEP under Pipeline Licence 128 is 1.33 km in length, 355.6 mm in diameter, and has  a maximum capacity of 350 TJ/day.

The WEP transports hydrocarbons from the:

  • Xyris Production Facility to the Waitsia Metering Station to the tie-in for the WEP on the Dampier Bunbury Pipeline for export
  • Waitsia Gas Plant to the Xyris Gas Plant for export.

The WEP is currently a non-scheme pipeline, and is subject to the access regime for non-scheme pipelines under Chapter 6A of the National Gas Access (WA) Law and Part 23 of the National Gas Rules (WA) (NGR (WA)).

The WA Economic Regulation Authority granted Category 1 and 2 exemptions under Part 23 of the NGR (WA) for the Pipeline that apply from 17 June 2022 to 17 June 2027.

Pipeline details

State:

WA

Type:

Transmission

Capacity:

350 TJ/day

Regulation:

Non-scheme

Additional Regulation:

Category 1 and 2

Owner:

AWE Perth Pty Ltd

Operator:

AWE Perth Pty Ltd

Length:

5 km

Gas Type:

Natural gas

Contact us

Title Date Documents
WA ERA Exemption Letter - Waitsia Export Pipeline 2022-06-17 Part 23 NGR (WA) Exemptions
Map - Waitsia Export Pipeline Pipeline Map
Rotate phone landscape for better viewing

WA: Xyris Pipeline

The Xyris Pipeline is a gas pipeline owned by AWE Perth Pty Ltd. The pipeline transports gas from the Xyris Gas Processing Facility to the Parmelia Gas Pipeline for export. It is a single use pipeline. The Xyris pipeline is currently a non-scheme pipeline, and is subject to the access regime for non-scheme pipelines under Chapter 6A of the NGL and Part 23 of the NGR. On 20 June 2019, the ERA granted a 5 year Category 1 and 2 exemption under Part 23 of the NGR for the Xyris Pipeline. 

Pipeline details

State:

WA

Type:

Distribution

Regulation:

Non-scheme

Additional Regulation:

Category 1 and 2 (expired)

Owner:

AWE Perth Pty Ltd

Operator:

AWE Perth Pty Ltd

Gas Type:

Natural gas

Contact us

Title Date Documents
ERA letter re exemption application - Xyris Pipeline 2018-06-20
Xyris Pipeline - Map
Rotate phone landscape for better viewing

WA: Woodada Lateral

The Woodada Lateral is a gas pipeline owned by AWE Perth Pty Ltd.

The pipeline is in care and maintenance following the cessation of production at the Woodada Gas Processing Facility. The Woodada Lateral is currently a non-scheme pipeline, and is subject to the access regime for non-scheme pipelines under Chapter 6A of the NGL and Part 23 of the NGR. On 12 September 2019, the ERA granted a five-year Category 1 and 2 exemption under Part 23 of the NGR for the Woodada Lateral Pipeline. 
 

Pipeline details

State:

WA

Type:

Transmission

Regulation:

Non-scheme

Additional Regulation:

Category 1 and 2

Owner:

AWE Perth Pty Ltd

Operator:

AWE Perth Pty Ltd

Gas Type:

Natural gas

Contact us

Title Date Documents
Exemption Application – Woodada Lateral (PL6) 2018-06-20
Woodada Lateral - Map
Rotate phone landscape for better viewing