Determination of Schedule for the Administered Price Cap

Expand Overview

On 21 May 2008, following the second round consultation process, the AEMC determined the final schedule which specifies the APC. The AEMC determined this schedule in accordance with clause 3.14.1(a) of the National Electricity Rules (Rules). In this schedule, the AEMC determined that the APC is $300/MWh for all regions in the National Electricity Market (NEM), for all time periods. The AEMC anticipated that it will review the APC schedule periodically when it considers necessary, but at least every three years. The AEMC considers such revision would appropriately negate the need for any indexation of the APC. This APC schedule also replaced the Tasmanian derogation under clause 9.45.2 of the Rules. The revised APC schedule became effective from the trading interval ending 4:30 AM Eastern Standard Time on 25 May 2008. A final determination report was published in accordance with clause 8.9(k) of the Rules. View more