Overview
On 18 June 2009, AEMO (formerly NEMMCO) submitted a Rule Change Request that principally seeks to transfer the current arrangements governing metering data service providers from a deed-based framework to a framework contained in Chapter 7 of the National Electricity Rules (Rules). On 6 May 2010, the Commission gave notice under section 99 of the National Electricity Law (NEL) for the publication of the draft Rule determination and draft Rule. The Commission invites submissions to the draft Rule determination by 1 July 2010.
This Rule Change Request proposes to:
The Rule Change Request also seeks to make certain other amendments to Chapter 7 of the Rules. Summarised briefly, the proposed changes would:
On 27 August 2009, the Commission gave notice under section 95 of the NELto commence consultation on the Rule Change Request. On 16 October 2009 submissions on first round consultation closed. On 10 December 2009, the Commission published a notice under section 107 of NEL to extend the publication date of the draft Rule determination to 1 April 2010. The Commission considered that this extension of time was necessary because the Rule Change Request raised issues of sufficient complexity.
On 1 April 2010, the Commission published a second notice under section 107 of the NEL to further extend the publication date of the draft Rule determination to 22 April 2010. The Commission considered that this extension of time is necessary because the Rule Change Request raised issues of sufficient complexity.
On 15 April 2010, the Commission published a third notice under section 107 of the NEL to further extend the publication date of the draft Rule determination to 6 May 2010. The Commission considered that this extension of time is necessary due to a material change in circumstances that affects this Rule Change Request.
On 6 May 2010, the Commission gave notice under section 99 of the National Electricity Law (NEL) for the publication of the draft Rule determination and draft Rule. The Commission invites submissions to the draft Rule determination by 1 July 2010.
Further, in accordance with section 101(1a) of the NEL, any person or body may request that the Commission hold a hearing in relation to the draft Rule determination. Any request for a hearing must be made in writing and must be received by the Commission no later than 13 May 2010.
All enquiries in relation to this project should be addressed to Marc Tutaan or Rory Campbell on (02) 8296 7800.
1. Initiation
AEMO’s Rule change proposal
AEMO’s proposed amendment to Chapter 7 of version 28 of the Rules (marked-up changes)
AEMO's proposed amendment to Chapter 7 of version 28 of the Rules (accepted changes)
AEMO’s proposed amendment to Chapter 10 of version 28 of the Rules
Notice - 27 August 2009
Consultation paper
Notice - 10 December 2009
Notice - 1 April 2010
Notice - 15 April 2010
AGL
CitiPower and Powercor
Grid Australia
Jemena
United Energy Distribution
EnergyAustralia - received 19 October 2009
SP AusNet - received 21 October 2009
Integral Energy - received 22 October 2009
Madeleine Kingston - Individual Stakeholder - received 16 April 2010
Madeleine Kingston - Individual Stakeholder - received 27 April 2010
2. Draft
Notice of Draft Rule Determination and Draft Rule - 6 May 2010
Draft Rule Determination
Draft Rule
Mark-up of Draft Rule
AEMO
Citipower and Powercor
EnergyAustralia
Madeleine Kingston - Individual stakeholder - main submission
Madeleine Kingston - Individual stakeholder - appendices to main submission
Origin Energy
SP Ausnet - received 2 July 2010
United Energy Distribution - received 2 July 2010
Kevin McMahon - Individual stakeholder - received 2 July 2010
Madeleine Kingston - Individual stakeholder - supplementary submission - received 3 July 2010
Integral Energy - received 7 July 2010
Kevin McMahon - Individual Stakeholder - supplementary submission - received 11 July 2010