Benefit/Impact
On 22 December 2011 the AEMC published its final determination in relation to this rule change. The Commission determined not to make the rule proposed as it considered that the market conditions necessary for its effective implementation are not yet in place. View more
This proposed rule change sought to allow the use of total factor productivity (TFP) methodology as an alternative economic regulation methodology to be applied by the Australian Energy Regulator (AER), in approving or amending price or revenue determinations for distribution network service providers.
On 22 December 2011 the AEMC published its final determination in relation to this rule change. The Commission determined not to make the rule proposed as it considered that the relevant market conditions necessary for its effective implementation are not yet in place.
On the 23 June 2008, the Victorian Minister for Energy and Resources submitted a rule change request to allow for the use of a TFP methodology as an alternative economic regulation methodology to be applied by the AER in approving, or amending, determinations for electricity distribution service providers.
On 24 July 2008, the Commission published a notice under section 95 of the National Electricity Law (NEL) advising of its intention to commence the rule making process, and the first round of consultation, in respect of the rule change request. However, as a result of the submissions received, on 21 November 2008 the Commission initiated a review entitled Review into the use of total factor productivity for the determination of prices and revenues.
Following the initiation of the review, the timing for publication of the draft rule determination was extended under section 107 of the NEL on three occasions:
The final report of the review was published on 7 July 2011.
A draft rule determination in respect of this rule change request was published on 29 September 2011.
1. Initiation
Rule Change Proposal for Total Factor Productivity Methodololgy in Distribution
Notice of First Round Consultation 24 July 2008
Notice of Time Extension Period 27 November 2008
Notice of Time Extension Period 23 July 2009
Report section 108A of the NEL
Notice of Time Extension Period 30 September 2010
AER
CitiPower, Powercor, ETSA
Country Energy
ENA
Energex
Ergon Energy
Integral Energy
Jemena
SP Ausnet
United Energy received 25 August 2008
EnergyAustralia received 27 August 2008
2. Draft
Notice of Section 99 - 29 September 2011
Draft Determination
Information Sheet
ENERGEX
Jemena Limited
Total Environment Centre
Ausgrid - received 11 November 2011
Department of Primary Industries (Victoria) - received 22 November 2011
3. Final
Final rule determination
Notice - 22 December 2011
Information sheet