Benefit/Impact
On 25 November 2010, the Commission gave notice under sections 102 and 103 of the National Electricity Law (NEL) of the making of the final Rule determination and Final Rule with respect to the Provision of Metering Data Services and Clarification of Existing Metrology Requirements Rule Change Request.
In brief, the Final Rule introduces (among other things) the following arrangements:
The Final Rule principally differs from the Draft Rule because the Final Rule makes the Responsible Person or AEMO responsible for the provision of metering data services. The Final Rule also provides detailed arrangements for the metrology of complex connection points.
All provisions of Schedules 1, 2, 3, 5 and 6 of the Final Rule commence on 16 December 2010. All provisions of Schedule 4 of the Final Rule commence on 20 January 2011.
On 18 June 2009, AEMO (formerly NEMMCO) submitted a Rule Change Request that principally sought to transfer the current arrangements governing certain metering data service providers from a deeds-based framework to a framework contained in Chapter 7 of the National Electricity Rules (Rules).
This Rule Change Request proposed to:
The Rule Change Request also sought to make certain other amendments to Chapter 7 of the Rules. In brief, the proposed changes would:
On 27 August 2009, the Commission gave notice under section 95 of the NEL to commence consultation on this Rule Change Request. On 16 October 2009, submissions on first round consultation closed. On 10 December 2009, the Commission published a notice under section 107 of NEL to extend the publication date of the draft Rule determination to 1 April 2010. The Commission considered that this extension of time was necessary because the Rule Change Request raised issues of sufficient complexity.
On 1 April 2010, the Commission published a second notice under section 107 of the NEL to further extend the publication date of the draft Rule determination to 22 April 2010. The Commission considered that this extension of time was necessary because the Rule Change Request raised issues of sufficient complexity.
On 15 April 2010, the Commission published a third notice under section 107 of the NEL to further extend the publication date of the draft Rule determination to 6 May 2010. The Commission considered that this extension of time was necessary due to a material change in circumstances that affected this Rule Change Request.
On 6 May 2010, the Commission gave notice under section 99 of the NEL for the publication of the draft Rule determination and draft Rule. The Commission invited submissions to the draft Rule determination by 1 July 2010.
On 5 August 2010, the Commission gave notice under section 107 of the NEL to extend the publication date of the final Rule determination to 25 November 2010. The Commission considered that this extension of time was necessary because submissions to this Rule Change Request raised issues of sufficient complexity.
Specifically, the following issues, which were raised in submissions, require detailed consideration:
In addition to the above key issues, there were over 150 technical drafting issues raised in submissions that attempted to clarify aspects of Chapter 7 and Chapter 10 of the Rules.
On 9 September 2010, in accordance with section 108A of the NEL, the Commission published a report giving reasons as to why the final Rule determination had not been made within 12 months after the publication of the notice under section 95 of the NEL. The Commission expected that the final Rule determination would be published on 25 November 2010.
On 16 September 2010 the Commission published a Consultation Paper on Specific Issues. In preparation for the final Rule determination, the Consultation Paper provided the Commission's position on the following issues:
An accompanying draft Rule, which articulated the Commission's policy position, was provided.
Submissions to the Consultation Paper on Specific Issues were due on 30 September 2010 and nine submissions were received.
1. Initiation
AEMO’s Rule change proposal
AEMO’s proposed amendment to Chapter 7 of version 28 of the Rules (marked-up changes)
AEMO's proposed amendment to Chapter 7 of version 28 of the Rules (accepted changes)
AEMO’s proposed amendment to Chapter 10 of version 28 of the Rules
Notice - 27 August 2009
Consultation paper
Notice - 10 December 2009
Notice - 1 April 2010
Notice - 15 April 2010
AGL
CitiPower and Powercor
Grid Australia
Jemena
United Energy Distribution
EnergyAustralia - received 19 October 2009
SP AusNet - received 21 October 2009
Integral Energy - received 22 October 2009
Madeleine Kingston - Individual Stakeholder - received 16 April 2010
Madeleine Kingston - Individual Stakeholder - received 27 April 2010
2. Draft
Notice of Draft Rule Determination and Draft Rule - 6 May 2010
Draft Rule Determination
Draft Rule
Mark-up of Draft Rule
AEMO
Citipower and Powercor
EnergyAustralia
Madeleine Kingston - Individual stakeholder - main submission
Madeleine Kingston - Individual stakeholder - appendices to main submission
Origin Energy
SP Ausnet - received 2 July 2010
United Energy Distribution - received 2 July 2010
Kevin McMahon - Individual stakeholder - received 2 July 2010
Madeleine Kingston - Individual stakeholder - supplementary submission - received 3 July 2010
Integral Energy - received 7 July 2010
Kevin McMahon - Individual Stakeholder - supplementary submission - received 11 July 2010
3. Final
Notice - 5 August 2010
Report - Section 108A of the NEL
Consultation Paper on Specific Issues (including accompanying draft Rule)
Notice 25 November 2010
Final Rule Determination
Final Rule
Mark up of Final Rule - Chapter 7, 10, 11 of the Rules
Citpower and Powercor
Ergon Energy
Jemena Electricity Networks
SP AusNet